Hawkswood School

Project: Hawkswood School

Delivery Schedule: Phase 1, 30 Modules, Phase 2, 23 Modules
Each phase was delivered over a one week period.

Trans2 Logistics project managed the delivery of 53 bays to a new school extension built in the Chingford area. Access was difficult due to a heavily built up residential area. However with accurate planning and assistance from the local Council this project was delivered seamlessly, on time and on budget. 